Engineering Department
Forest Avenue Sewer and Storm Drain Project
Forest Avenue Construction Status & Schedule Update
Date: March 31, 2017
Status:
Speed Feed Back Signage to be completed within 2 weeks, Speed tables have been installed, and are under review for compliance with specifications.
Work Pending:
1) Punch list consisting of any outstanding items has been submitted to contractor for corrective actions including asphalt scheduled for early spring 2017.
2) Retainage will be held for maintenance period.
If you have any comments, concerns or questions please call Warren Hall, Town Engineer at 418-0413
The Town appreciates all of your patience with this project.