Forest Avenue Construction Status & Schedule Update as of November 30, 2016

Engineering Department
December 1, 2016

Date: November 30, 2016

Status:

Finish Course including speed tables have been installed, final inspection & acceptance to be completed by project engineer

Work Pending:

1) Striping along centerline, fog lines & speed tables as soon as weather permits

2) Signage: Truck Restriction, Speed Hump, Driver Speedback Sign scheduled for week of December 5

3) Punch list consisting of any outstanding items to be submitted to contractor for corrective actions including asphalt scheduled for week of December 12

4) Final clean up scheduled for week of December 12

5) Retainage will be held for maintenance period

If you have any comments, concerns or questions please call Warren Hall, Town Engineer at 418-0413

The Town appreciates all of your patience with this project.